Westport RTM March Meeting: $3.1 Million Appropriated for Public Works Projects

March 7th, 2023 Agenda & Results

Westport’s Representative Town Meeting met via Zoom for a session beginning at 7:30 and adjourning at just after 9:40 this evening. Over 3 million dollars were appropriated for three different projects for the Department of Public Works, all of which involved the community’s sewer systems - including a new pump station on Riverside Avenue and adding several streets to the existing sewer & water lines.

Click here to read all meeting materials - including requests and proposals and their respective information.

1. To take such action as the meeting may determine, upon the recommendation of the RTM Rules Committee, to approve an amendment to Section 22-1 of the Code of Ordinances, establishing new and/or reaffirming voting districts following the 2020 Census as provided in Section C5-2 of the Town Charter. First reading. 

No vote needed. First reading completed.

2. To take such action as the meeting may determine, upon the request of the Director of Public Works, to approve an appropriation in the amount of $1,900,000.00 along with bond and note authorization, to the Sewer Reserve Fund Account for the replacement of Pump Station #3 Force Main Sewer Line and Pump Station Upgrades. 

Unanimously approved by all present RTM members.

3. To take such action as the meeting may determine, upon the request of the Director of Public Works, to approve an appropriation of $416,000.00 along with bond and note authorization to the Municipal Improvement Fund Account for additional funding for construction to extend the Sanitary Sewer System to Whitney Street, Roseville Road, Fernwood Road, Plumtree Lane, Pamela Place and Ledgemoor Lane. 

Unanimously approved by all present RTM members.

4. To take such action as the meeting may determine, upon the request of the Director of Public Works, to approve an appropriation of $790,000.00 along with bond and note authorization to the Municipal Improvement Fund Account for additional funding for construction to extend the Sanitary Sewer System to Evergreen Avenue, Evergreen Parkway, Tamarac Road, Lone Pine Lane, Gorham Avenue, Compo Road North and Brookside Drive.

Unanimously approved by all present RTM members.

Previous
Previous

Cross Highway Road Improvement Info Session Slated for March 14

Next
Next

Morning Weather Report